East Leake Schools - Nottinghamshire |
| Client: Nottingham City Council |
| Contract Value: £1 million |
|
One of the key factors in the performance of the new roof was being able to absorb sound and still give good attenuation.
With a total project value of £1 million this is another example of Weatherwise’s ability to deliver first class roofing and cladding systems for new or existing structures by taking total control of this element of the project from start to finish.
Keybemo standing seam sheets with perforated long span structural decking and Single ply roof membrane and Kingspan architectural wall panel.
|
|
Siddal Moor Sports College |
| Client: Carillion Plc |
| Contract Value: £ 1.4 million |
|
Weatherwise have been awarded a new contract, as part of the Rochdale BSF Programme, to built by Carillion Plc.
The Carillion-led Inspired Spaces consortium has won the £200 million Rochdale Building Schools for the Future (BSF) contract.
The contract is part of the £55 billion BSF scheme to renew the schools estate by 2023.
Carillion expects to deliver 13 new or refurbished schools in three phases over four years for the Rochdale BSF programme, as part of a local education partnership (LEP) that includes Rochdale Borough Council and Building Schools for the Future Investments.
Weatherwise have successfully secured School No 2 -
Siddal Moor Sports College.
Our £ 1.4 million contract encompassed the design, supply and installation of the total building envelope package.
Weatherwise were selected by the main contractor as we provided the most competitive solution for the design criteria, enhanced value engineering and eliminate any potential interface problems.
Weatherwise Managing Director, Wayne Little commented:
“ We are over the moon to be award the second school straight after our success on school one. We fully intend to embrace this opportunity. With the sustainable opportunity of a potential further 11 schools, our team need to be fully focus on delivering a success project for Carillion “ Right first time”. The whole team has been outstanding, going the extra mile to get the Rochdale project over the line."
|
|
Hollingworth Business and Enterprise College |
| Client: Carillion Plc |
| Contract Value: £ 1.6 Million |
|
Weatherwise have been awarded a new contract, as part of the Rochdale BSF Programme, to built by Carillion Plc.
The Carillion-led Inspired Spaces consortium has won the £200 million Rochdale Building Schools for the Future (BSF) contract.
The contract is part of the £55 billion BSF scheme to renew the schools estate by 2023.
Carillion expects to deliver 13 new or refurbished schools in three phases over four years for the Rochdale BSF programme, as part of a local education partnership (LEP) that includes Rochdale Borough Council and Building Schools for the Future Investments.
Weatherwise have successfully secured School No 1 - Hollingworth Business and Enterprise College.
Our £ 1.6 million contract encompassed the design, supply and installation of the total building envelope package.
Weatherwise were selected by the main contractor as we provided the most competitive solution for the design criteria, enhanced value engineering and eliminate any potential interface problems.
Weatherwise Managing Director, Wayne Little commented:
“ We are very excited about securing our first BSF project with Carillion. We fully intend to embrace this opportunity. With the sustainable opportunity of a potential further 12 schools, our team need to be fully focus on delivering a success project for Carillion “ Right first time”. The whole team has been outstanding, going the extra mile to get the Rochdale project over the line."
|
|
Core Technology Facility |
| Client: HBG Construction Ltd |
| Contract Value: £3,000,000 |
|
Weatherwise were awarded the contract to work on the Core Technology Facility, built by Manchester Innovations Limited, responsible for marketing the outputs of research from the University of Manchester and elsewhere.
The £3 million contract encompassed the design, supply and installation of the total envelope package. The specification included low pitch roof panels and flat panels with a single ply membrane.
Luxalon wall cladding was been specified, with structural glazing, curtain walling and windows, and the project also required terracotta rainscreen tiles, louvres and sunscreening with an abseil and mansafe system.
Weatherwise were selected by main contractor HBG Construction Ltd as they could provide the most competitive solution for the design criteria and eliminate any potential interface problems.
The site is on the corner of Upper Brook Street and Grafton Street in Manchester with the site boundary very close to the building line, therefore, Weatherwise expertise in restricted access projects with associated safety considerations was another contributing factor in winning the contract.
|
|
Matthew Boulton College |
| Client: HBG Construction Ltd |
| Contract Value: £900,000 |
|
Information to appear shortly
|
|
Fazakerley High School - Liverpool |
| Client: TBC |
| Contract Value: £450,000 |
|
One of the key factors in the project was the roll-forming on site of the standing seam roof sheets, which would otherwise have been at risk during transportation and hoisting.
Particular attention had to be paid to the perimeter details to ensure there compliance with Part L of the new building regulations.
Another of the key factors in the project is the need to manufacture the long length standing seam sheets that will be used in the new roof on site, as they would be very difficult to transport.
- Self-curving aluminium standing seam insulated roof with Kingspan architectural wall panels
- Value: £450,000
|
|
|
|
|
|